In the municipal plan of primary school upgrading, the municipality of Brescia (through A2A) decided to build a new technological plant to provide the energy needs of three schools in the town fraction of Buffalora.

To sum up, the intervention saw the realization of a new cogeneration power station with two heating condensing boilers and a 65 kW micro gas-turbine. The heat produced is sent to the four buildings (a kindergarten, a primary school, a secondary school and a gym) through a small heating network.

Furthermore, on the rooftop of the power station solar panels were installed to produce domestic hot water and electrical energy.

Engineering Services provided:

Preliminary design, definitive design, Detailed design, construction design, realization of electro-mechanical works.

committente
customer

A2A

fruitore
End-User

Comune di Brescia

ubicazione
location

Brescia

periodo
period

2007-2008

importo
amount of works

€. 500.000